Norway Hits the Brakes on Its Data Center Boom
Norway's transmission system operator Statnett paused new grid reservations for data centers on 9 November, the same day the government announced a licensing scheme that will keep out new crypto mining. The grid reservation halt will last until at least August 2027, when a new system is set to come into effect. Both moves come as data center demand threatens Norway's long-standing power surplus. A queue larger than the country's peak demand Data centers have asked for about 34 gigawatts (GW) of grid capacity in Norway, well above national peak…
Norway's transmission system operator Statnett paused new grid reservations for data centers on 9 November, the same day the government announced a licensing scheme that will keep out new crypto mining.
The grid reservation halt will last until at least August 2027, when a new system is set to come into effect.
Both moves come as data center demand threatens Norway's long-standing power surplus.
A queue larger than the country's peak demand Data centers have asked for about 34 gigawatts GW of grid capacity in Norway, well above national peak demand of about 25 GW.
PublisherOilPrice
Categorycrypto
Published2026-11-26T20:00:00Z
Indexed7m ago
More from OilPrice
Latest in crypto
- Bluefin to shut down perps, refocus on spot trading and tokenized RWAsCointelegraph · 23m ago
- Ethereum Sets December 15 Date for Delayed Glamsterdam Testnet UpgradeDecrypt · 33m ago
- ESMA to overhaul EU’s MiCA crypto register in 2027Cointelegraph · 2h ago
- Bitcoin Treasury Corporation GAAP EPS of C$2.25, revenue of C$0.08MSeeking Alpha · 4h ago
- Bitcoin Treasury Corporation GAAP EPS of $2.25, revenue of $0.08MSeeking Alpha · 4h ago
FinancePulse indexes headlines and short summaries from 23 institutional publishers. This page does not republish the full article — all rights belong to OilPrice.